|

November 21, 2003
Santa Clara Valley Water District’s Solar project:
Cost-effective and eco-friendly
By Candy Richter
Staff Writer
True to the company’s “think blue, think green, think
smart” motto, Santa Clara Valley Water District has adopted
an aggressive plan to shift its energy source from the traditional
electricity-based model to a natural gas and solar model, which
is projected to save the company an estimated $150,000 per year
in energy costs.
In addition to the yearly cost savings, converting to this new
energy-efficient mode will reduce the facility’s pollutant
outputs of carbon dioxide (greenhouse effect gasses), sulfur dioxide
(acid rain), and nitrogen dioxide (smog), adding ecological benefits
to the project’s bottom-line improvements.
A central component of the conversion project will be the construction
of two “solarports” located directly in front of SCVWD’s
main headquarters on Almaden Expressway. The ports, designed by
the Sacramento-based architectural firm of Mogavero, Notestine &
Associates, will provide the support system for the multi-crystalline
silicon solar cells, which will produce 105 kilowatts of energy.
Additional solar panels, installed on the roof of the Almaden campus
administrative building, will produce an additional 95 kw, for a
total of 200 kw, or roughly 20 percent of the facility’s energy
needs.
Working in conjunction with the solar arm of the project will be
a natural gas-fired “cogeneration” system that will
include both a 1,000 kw natural gas electrical generator and a heat
recovery unit that will serve as the heating and cooling source
for the facility, thus eliminating any thermal impact on the surrounding
area.
“We’ve seen an increase of 50 percent to 60 percent
in our power costs,” says Stan Kaut, manager of the water
utility engineering unit at SCVWD. “So we started looking
at alternative sources for energy—wind, cells, even possibly
getting into the power business ourselves—but solar was the
real stand-out.”
Although the total project cost to SCVWD is estimated at $4.6 million,
when the various state-funded incentives for converting to “green”
energy are factored in, the actual expenditures will come in at
$2.3 million, which will be funded by SCVWD Capitol Project Program
funds.
“These funds are used for a variety of improvement projects,”
adds Kaut. “For example, when we needed to change the pump
drive out at Pacheco. When these projects come up, they are analyzed
and prioritized. A project that would impact a water filtering system,
for instance, would take precedence over something like the solar
project. It’s based on the impact to the system. This project
got the go-ahead because of not only the cost savings, but also
the environmental benefits.”
Adding to the cost effectiveness of the solarport project is the
type of photovotive cells the district plans to use. Provided by
Powerlight, the recognized leader in photovotive technology, the
multi-crystalline panels are virtually maintenance-free and can
withstand impacts up to 70 miles per hour.
“As a public utility, we are required to put our jobs out
for bid,” explains Kaut. “As it turned out, Powerlight
saw this as a real opportunity for them and came in low to get the
job. Now we have the leader in this field providing the cells and
they get the opportunity to work with our facility. It was a real
win-win.”
According to Associate Electrical Engineer Arvind Tailor, SCVWD
built maintenance training into its contract with Powerlight. “We
are getting both a maintenance manual and training for our staff,
so we will be completely self-sufficient.”
Looking at a direct cost-to-cost comparison, current energy costs
to SCVWD run approximately 14 cents per kilowatt hour. On the new
system, the average costs will be only 8 cents per kwh. SCVWD estimates
a five-year payback for the natural gas portion of the project and
an average estimate of 12 years on the solar portion.
“We’re very proud of this project,” says Kaut.
“Eventually, we plan to have an educational kiosk display
at headquarters to show the public how much we’re producing,
how much we’re saving, and what benefits we’re bringing
to the environment through this conversion. We want to share this
with the public.”
In fact, sharing with the public has been the most common complaint
about this and other SCVWD undertakings. “I feel like this
was a ‘done deal’ before the community even had a chance
to get involved,” says Almaden activist Yvette Osborne, who
found out about the solar project in the SCVWD newsletter. “They
need to let us know what’s going on, get input, share information.
[The neighbors] are a part of this community, and the district needs
to respect that.”
Coming on the heels of the community neglect allegations regarding
the district’s handling of the Penitencia Water Treatment
Plant construction in East San Jose, SCVWD has received failing
marks in the community outreach area, a reputation they are moving
quickly to rectify.
“QUOTE FROM MIKE”
Photo 1 top of port: The two solarports will produce a combined
200 kilowatts of energy, roughly 20 percent of the Almaden campus’
energy needs. Utilizing the latest in photovotive technology, the
multi-crystalline panels are easy to maintain and easy to repair,
virtually eliminating upkeep costs. Although resilient enough to
withstand a 70 mph impact, the district has 10 spare panels on hand
“just in case.” The new carports will also be equipped
with four electric vehicle (EV) recharge outlets.
Photo 2 top of roof: Solar planes on the roof of the SCVWD administration
building were placed to receive maximum sun exposure. “We’ve
considered everything,” says Stan Kaut, SCVWD’s manager
of the water utility engineering unit. “We even looked at
the reflective impact of air traffic.” Providing the balance
of the facility’s energy needs will be a 1,000-kilowatt natural
gas generator, to be located approximately 150 yards from the intersection
of Coleman and Almaden Expressway, in a maintenance yard.
Photo 3 side of port: Although there was initial community skepticism
surrounding the $4.6 million cost of the solar project, state rebates
and other incentives will cut the total project cost by half, which
will be funded by SCVWD Capitol Project funds. “This project
will not cost the consumer,” says Kaut. “If anything,
by reducing our energy costs, which are built into our rates, we
can keep our customer’s costs down.”
|